V-TAI JD-3

Electrical Requirements for Bakery Dishwashers

Most "installation didn't go smoothly" stories start with electrical mismatches. Here's what you need to know before you order.

JD-3 Standard Electrical Specs

  • Voltage: 380V three-phase (also written as 380V/3N/50Hz)
  • Current: 21.5 A
  • Total power: 13 kW
  • Cable requirement: 5-core (3 phases + neutral + earth), 4 mm² recommended
  • Breaker: Dedicated 32 A three-phase circuit breaker
  • Grounding: Required and must be verified

Why 380V Three-Phase?

Three-phase power delivers significantly more power efficiently than single-phase. The JD-3's 9 kW booster heater needs three-phase to ramp up quickly enough for the 2-minute cycle. A single-phase 220V circuit could not deliver this power without an unreasonably long cycle time.

Regional Voltage Variations

RegionStandard voltageJD-3 fit
Europe, Australia, GCC, Russia, China380V three-phaseDirect fit
Brazil, Argentina, parts of LATAM380V three-phaseDirect fit
Mexico, Caribbean220V single-phase typicalConversion or 220V option
United States208V three-phase common in commercial208V option available
Japan200V three-phase200V option available
Thailand, Vietnam, Indonesia380V three-phaseDirect fit

If You Only Have 220V Single-Phase

Two options:

  1. Install 380V three-phase circuit. A licensed electrician can run a new circuit from your building's main distribution panel. Cost varies by country and circuit length: $300–$1,500 typically.
  2. Order JD-3 in 220V configuration. We offer a 220V option that uses a smaller booster heater (6 kW instead of 9 kW). Cycle time extends to ~150 seconds (vs 120 seconds standard). Specify "220V single-phase" in your quote request.

Dedicated Circuit Required

Do NOT share the JD-3's circuit with other equipment. Sharing causes:

  • Voltage drops when other equipment cycles on (refrigerators, ovens)
  • Booster heater inability to reach 82°C
  • Premature breaker tripping
  • Potential damage to control electronics

Grounding Is Critical

Improper grounding is the most common cause of commercial dishwasher electrical failures. Verify with your electrician:

  • Earth wire connected to the machine's dedicated grounding lug
  • Ground continuity tested and recorded
  • RCD (residual current device) on the circuit

Energy Cost Estimation

13 kW for 2 minutes per cycle = 0.43 kWh per cycle. At commercial rates of $0.12–$0.25 per kWh (depending on country):

  • 30 cycles/day × 300 days/year = 9,000 cycles/year × 0.43 kWh = ~3,870 kWh/year
  • Annual electricity cost: $465–$970

Heat recovery module reduces this by 15–25%.

Installation Cost

Have a licensed commercial electrician do the installation. Time required: 45–90 minutes. Cost varies by country: $80–$300 typical. Don't DIY this — incorrect electrical install voids warranty and creates fire risk.

Ready to End Manual Tray Washing?

Get a custom quote in 12 hours. CE-certified, from $4,400 FOB Shenzhen.